Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

What are the 3 features of a typical seigneurie
Why was is difficult for the Arab people to form one nation?
Which of the following can be considered fossils? a. a 1 billion year-old rock. b. a 1 billion year-old piece of amber. c. a 1 billion year-old piece of amber w
Why was is difficult for the Arab people to form one nation?
An airplane travels 3,260 kilometers in 4 hours. What is the airplane’s average speed?
Natalie earns $2.50 for each cd she sells and $3.50 for each dvd she sells.  Natalie sold 45 dvds last year.  She earned a total of $780 last year selling cds a
By the mid-1700s, the largest city in the colonies was (A) New York (B) Boston (C) Philadelphia (D) Charleston (E) Wilmington, Delaware
which seismic wave moves through earth at the fastest speed?
the cafeteria has 45 square  tables that can be pushed together to form one long table for the lacrosse team's banquet. Each square table can seat one person on
The length of a diagonal of a cube with edge length 25cm