if 10 man can work 6hours.How many more men are needed towork in 4 hours​

Respuesta :

mathstudent55
mathstudent55 mathstudent55
  • 03-12-2021

Answer:

5 more men

Step-by-step explanation:

10 men do a job in 6 hours.

To do the job in 2 hours, 1/3 of the time, you need 3 times as many men.

30 men do a job in 2 hours.

To do the job in twice the time, 4 hours, you need half the men.

15 men do a job in 4 hours.

15 men - 10 men = 5 men

You need 5 more men.

Answer Link

Otras preguntas

How does the chain of command facilitate the operations of a large structured organization?
The eastern edge of the North American continent is not the same as the eastern boundary of the North American plate. The eastern edge of the North American con
In parallelogram RELA you are given that the measure of angle R = 110 degrees. Find the measure of angle E? Help me solve thiss
What is the altitude of the north celestial pole for an observer located on the earth's equator?
Why is it smart to keep you cool when making claim, and how should you go about it?
Find the length of the missing side of the right triangle. 5 ft. 12 ft. What’s x
One multicellular organism is a cube. Each of its sides is 3 cm long. Each of its cells is 1 cm. How many cells does it have? If each side doubles in length how
The best teacher's day slogans
What is the solution to the linear equation? 를 글 - + 5 - X 6 x = -5 Ox= 0 x= Ox=5
Who is Bartolomé de las Casas?