When looking at a program board at the end of program increment (PI) planning, what does it mean when a feature is placed in a team's swim lane with no strings

Respuesta :

IfeanyiEze8899 IfeanyiEze8899
  • 04-01-2021

Answer:

It simply means that other teams can independently complete the feature.

Explanation:

PI or program increment is a planning interval during which an agile release train (ART) plans and produces working and tested software and systems. It takes a duration of 8 to 12 weeks

Agile teams can access and independently complete various ARTs found in their swim lanes with no strings.

Answer Link

Otras preguntas

if the roots of x²-7x+k=0 are m and m-1, find the value of the constant k​
SOMEONE PLEASE HELP ILL MARK BRAINLIEST PLEASE FOLLOW THE LEARNING TARGETS
what are the common forms of African literature? describe them​
有人可以帮忙吗?我解决不了..... 是高考题
can somebody please help me I'm begging you I'm on my last question​
Please help me with number 4 thank you so much!
I can’t figure this out. Help is greatly needed
what is the quontient of 72000+900?​
Select the correct answer. Which statement is true about this quadratic equation? y = x^2 - 11x + 7 A. There is one complex solution. B. There are two real solu
đảng cộng sản việt nam ra đời vào thời gian nào