contestada

if 12 people can finish a job by 5 days how many days will be required finish the same job by 10 people

Respuesta :

ishashunnny
ishashunnny ishashunnny
  • 01-09-2020

Answer:

4

Step-by-step explanation:

12p=5d

1p=5/12

10p=4.1666

≈4 days

Answer Link

Otras preguntas

In a proportion , where x can’t equal 0 and y can’t equal 0, which of the following are equivalent to 5/8 =x/y A. 5/x = 8/y B. 5+8/8 = x+y/y C. 8/5 =y/c D. Th
A cyclist averages 50 m/s. If the course is 80,000m long. How many seconds will it take to complete the course?
Jim and David decide to arm wrestle to determine who is stronger. Jim uses all of his strength, but David wins and is able to push Jim's hand to the table. The
Historically, which age group has been least likely to turn out to vote?
How to conduct research on vulnerable groups ethically?
Two roads that cross at right angles are used as the coordinate axes for a city map. A hospital is located at the point (−1.25, −5.5) -1.25, -5.5 . How far is
Which strategy allowed Germany to have immense success at the beginning of World War Two
True or false? the growth of villages into cities generally resulted in a reduced rates of infectious disease. a. True b. False
What was the major result of the Great Depression of 1929
The time it takes a spinner to stop completely is 12 seconds. If the spinner completes 6 revolutions in this time, what was the average angular velocity of the